This is a record, not a portfolio: every project and contract on the company’s record, and two projects documented from assessment to execution. Where nothing was recorded, nothing is claimed.
A treatment bed on the works area, lines laid through the material.
Projects and contracts
The complete record
Every project and contract in the company’s official resume, newest delivery first. The two projects with pages of their own follow the list, with photography and a full account.
IEBCO projects and contracts
No.
Project
Client
Contract Date
Delivery Date
01
Recycling, Remediation and Environmental Disposal Services for Oil-Based Drill Cuttings Generated by the Rashadat II Project
Client Petro Gohar Farasahel Kish (PGFK)
Contract Date 8 Feb 2026
Delivery Date 2027–28
02
Biological, Environmentally Compatible Remediation of Oil-Contaminated Sludge and Soil and Petroleum Waste, Tehran Oil Refining Company
Client Tehran Oil Refining Company (TORC)
Contract Date 19 May 2025
Delivery Date 2027–28
03
Remediation of 400 Tonnes of Petroleum-Contaminated Soil at the Shahid Nourbakhsh Depot, Mahshahr
Client Oil Products Distribution Company, Abadan Region
Contract Date 2 Sep 2026
Delivery Date 2026–27
04
Localisation of Technical Know-How and Production of BIO OSD, a Biological Marine Oil-Slick Removal Agent Product: BioOSD
Client Iranian Offshore Oil Company (IOOC)
Contract Date 22 May 2023
Delivery Date 2024–25
05
Provision of Bioremediation Services, Forouzan Oilfield Development Project
Client MI Services Ltd. Petropars Ltd (PPL)
Contract Date Mar 2022
Delivery Date Dec 2024
06
Waste Management and Bioremediation Services
Client PGFK
Contract Date 4 Dec 2021
Delivery Date 2023–24
07
Provision of Waste Management Services
Client DCI
Contract Date 9 Feb 2021
Delivery Date 2023–24
08
Research Services for the Project “Consulting, Knowledge Transfer, Desludging, Dredging, and Recycling of Oily Wastewater and Petroleum Waste on Lavan Island”
Client IOOC
Contract Date 2018–19
Delivery Date 2022–23
09
Supply of Consumables for the Project “Consulting, Knowledge Transfer, Desludging, Dredging, and Recycling of Oily Wastewater and Petroleum Waste on Lavan Island”
Client IOOC
Contract Date 2018–19
Delivery Date 2022–23
10
Bioremediation of Drilling Waste in the Lavan Operational Area
Client CIRON
Contract Date 2019–20
Delivery Date 2020–21
11
Supply of the Bioremediation agent, and consulting and monitoring the implementation of bioremediation operations required for biological treatment of the hydrocarbon contaminations in the polluted site containing soil and sludge residue from oil-drilling activity in oil well (Iraq - Samawa - Block 12) Read the case study
Client Zhongman Petroleum and Natural Gas Group Co., Ltd (Iraqi Branch)
Contract Date 2019
Delivery Date 2019
12
Technology Development, Local Formulation Design and Prototype Production of a Biological Marine Oil-Slick Collecting Agent (Bio-OSC)
Client Iranian Oil Terminals Company (IOTCO)
Contract Date 2017–18
Delivery Date 2018–19
13
Development of Technical Know-How and Production of a Bio-Based Oil-Slick Removal Agent (Bio-OSD), Phase 2: Semi-Industrial Production Product: BioOSD
Client IOTCO
Contract Date 2016–17
Delivery Date 2017–18
14
Development of Technical Know-How and Production of a Bio-Based Oil-Slick Removal Agent, Phase 1: Laboratory Prototype Product: BioOSD
Client IOTCO
Contract Date 2015–16
Delivery Date 2016–17
15
Commercialisation and Industrial Production of a Microbial Powder for Degrading Petroleum Contamination
Client IOTCO
Contract Date 2015–16
Delivery Date 2015–16
16
Biological Treatment of Liquid and Solid Waste at the Oil-Based Mud Plant or Other Sites Proposed by the Client Read the case study
Client National Iranian South Oil Company (NISOC)
Contract Date 2012–13
Delivery Date 2012–13
The delivery date is the one the company resume records; on its own it does not state that a project was completed. Dates the source gives in the Iranian calendar are shown in the Gregorian calendar at the same precision, so a year that spans two Gregorian years is shown as both.
Case studies
Two projects documented end to end
Both have assessment data, field photography and a recorded scope, so each gets a page of its own.
1391·کارخانه گل حفاری پایه روغنی، جنوب شرقی اهواز، کیلومتر 50 جاده اهواز–امیدیه
Years of plant operation had left oily mud and contaminated waste accumulated in the pits downstream of the facility. The project took that waste stream through four stages, from recovering the oil fraction to putting vegetation back on the ground.
The works on this project were executed jointly by Industrial and Environmental Biotechnology Company and ACECR Applied Sciences Research Institute.
Clean oil recovered
727 bbl
Hydrocarbon-contaminated wastewater treated
3,065 bbl
Executed jointly by Industrial and Environmental Biotechnology Company · ACECR Applied Sciences Research Institute
A project in Block 12, Samawah, Iraq, on soil and sludge left by drilling operations. IEBCO worked as sub-contractor: supplying the bioremediation agent, and providing consulting and technical monitoring for the treatment operation.